A channel has opened for vessels clearing wreckage at the Baltimore bridge collapse site

The fallen Francis Scott Key Bridge in Baltimore is pictured Sunday, March 31, 2024, where divers assisted crews with the complicated and meticulous operation of removing steel and concrete. (AP Photos/Mike Pesoli)

BALTIMORE — The U.S. Coast Guard has opened a temporary, alternate channel for vessels involved in clearing debris from the collapsed Francis Scott Key Bridge in Baltimore, part of a phased approach to opening the main shipping channel leading to the vital port, officials said Monday.

Crews are undertaking the complicated work of removing steel and concrete at the site of the bridge’s deadly collapse after a container ship lost power and crashed into a supporting column. On Sunday, dive teams surveyed parts of the bridge and checked the ship, and workers in lifts used torches to cut above-water parts of the twisted steel superstructure.

ADVERTISING


Officials said the temporary channel is open primarily to vessels that are helping with the cleanup effort. Some barges and tugs that have been stuck in the Port of Baltimore since the collapse are also scheduled to pass through the channel.

Authorities believe six workers plunged to their deaths in the collapse, including two whose bodies were recovered last week.

Maryland Gov. Wes Moore said at a Monday afternoon news conference that his top priority is recovering the four remaining bodies, followed by reopening shipping channels to the port. He said he understands the urgency but that the risks are significant. He said crews have described the mangled steel girders of the fallen bridge as “chaotic wreckage.”

“What we’re finding is it is more complicated than we hoped for initially,” said U.S. Coast Guard Rear Admiral Shannon Gilreath.

Moore said crews used a large crane to lift a 200-ton (180-metric ton) span of the bridge, a task that took 10 hours. He said the piece was considered a “relatively small lift” in the grand scheme of the recovery effort, which he called enormous.

Moore said crews would lift another 350-ton (317-metric ton) piece from the bridge later Monday as weather allows.

Leave a Reply

Your email address will not be published. Required fields are marked *

*

By participating in online discussions you acknowledge that you have agreed to the Star-Advertiser's TERMS OF SERVICE. An insightful discussion of ideas and viewpoints is encouraged, but comments must be civil and in good taste, with no personal attacks. If your comments are inappropriate, you may be banned from posting. To report comments that you believe do not follow our guidelines, email hawaiiwarriorworld@staradvertiser.com.